United Electric Co. Commercial Hospitals

VA ELECTRICAL DISTRIBUTION Phase 1,2,3, and 4

Original Subcontract Amount: $13,000,000
Award Date: May 2008
Actual Completion: January 2012
Your Performance Evaluation by Owner: Very Good
Your Performance Evaluation by Prime: Very Good
Owner: Veterans Administration
Contact: Please contact Project Manager Larry Farrell for further information.

General Scope of Project

Four phase project to replace medium voltage and 480-Volt distribution systems without disrupting an operating occupied hospital campus

Role and Self-performed Work

As a prime contractor, United Electric worked with engineering firms to design and develop a work plan to replace existing antiquated substations and generators with new modern and increased capacity systems. Work included building temporary substations and generator to change out (6) unit substations, (15) ATS systems, paralleling gear and (3) 2000KW generators.