GE DATA CENTER

8700governors 1200xx3008 1697 0 103 Jpg
Article Im1817 Ge S Leed Platinum Data Center Jpeg Jpg
Group 324

Design/Assist

Original Subcontract Amount: $21,000,000

Award Date: October 2007

Completion: August 2008

Your Performance Evaluation by Owner: Very Good

Your Performance Evaluation by Prime: Very Good

Owner: General Electric

Contact: Please contact Project Manager Phil Harris for further information.

 

General Scope of Project

The scope of this project included the design-build construction of a new 450,000 square feet Tier 5 data center for General Electric Appliance Park.

 

Role and Self-performed Work

United Electric was a prime subcontractor on this project. We were responsible for the installation of all medium- and low-voltage power distribution, fire alarm, mass notification, biometric security systems including POE CCTV. Additional scope included UPS, Generation with programmable switch gear and 15 KV power station. Project was a fast track installation, with a 9 month construction schedule, and over 150,000 man hours worked.